CASE

Community Academic-Service Entrepreneur

Program Plan

Program Element Month Example 1
Fall Award
Example 2
Spring Award
1. C2PF commitment and date 1 Apr 1 Sep 1
2. Establish project plan 1 Apr 15 Sep 15
3. Secure approvals; commit date 2 May 15 Oct 15
4. "Semester ahead" announcement 2 May 20 Oct 20
5. Recruit selection committee 4 Jul 15 Dec 15
6. Distribute applications 6 Sep 1 Feb 1
7. Receive applications 7 Oct 1 Mar 1
8. Evaluate applications 7 Oct 15 Mar 15
9. Advise winner(s) 8 Nov 1 Apr 1
10. Present winner grant(s) 8 Nov 15 Apr 30
11. Monthly email update to C2PF During project
12. Create project video(s)
13. Student submits final report After project completion
14. Update websites, data & videoo
15. Establish next cycle plan & dates